Garmco Re-Melt expansion project progress

Garmco Re-Melt expansion project progress-FIVES

In September 2016, some of the main pieces of equipment were delivered to site from Jasco’s workshops located in Riffa. The casing of the first Holding & Melting Furnace arrived on site on September, 08th, slightly ahead of the master schedule. This large size casing (9m x 10m x 5m) weighing 72 MT was delivered in one piece, and immediately dropped off at its final location. The second furnace arrived safely on September, 15th.

Next step: the construction of the main building alongside with the final furnace assembly and the installation of other equipment.